Viewing the Activity

From the Case Display screen under the Case Progress Summary tab, right mouse click over an activity. Click on View.


Completing an Activity

1. From the Case Display screen under the Case Progress Summary tab, right mouse click over an activity and click on Update Activity

2. The Update Activity screen will pop up. From the drop down menu, change the Status to Completed

3. Update the completed on field to specify the date and time the activity was completed.


Activity Progress Summary1. From the Case Display screen you are able to see the activity progress summary by clicking on the Activity Progress Summary tab



 
 
 

Recent Posts

See All
SMS Service in ChilliDB

ChilliDB provides an integrated SMS service that allows organisations to send text messages directly from the system. Before using this...

 
 
 
ChilliDB Backup Policy

At ChilliDB, we implement a structured and secure backup strategy to ensure business continuity and data integrity. Our backup system is...

 
 
 

Comments


bottom of page